Camas Creek Road (NFSR 258) and Fish Habitat Improvement Project, Phase I
The project would reroute part of NFSR 258 away from the streambank, install a new channel-spanning bridge in a more stable location, rehabilitate the existing ford crossings, and decommission the original road.
Project Summary
Location Summary:
Camas Creek Road NFSR 258 near Meyer%u2019s Cove
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/13/2024 |
Decision | 07/2025 (Estimated) |
Implementation | 07/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Cobalt Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Road Management
Project Activity:
Species Habitat Improvements; Road Maintenance; Watershed Improvements
Current Status:
In Progress
Forests:
Salmon-Challis National Forest
Districts:
Salmon-Cobalt Ranger District
States:
Idaho
Counties:
Lemhi
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kelly Schade
311 McPherson
Salmon, ID 83467
208-756-5229
kelly.schade@usda.gov
Last Updated: 3/18/2025