East Kentucky Power Cooperative Special Use Permit STE4062 Amendment
Rebuilding the 69 kV Transmission Line under permit STE4062 that has a permitted right-of-way width of 100-feet and length of 8.6 miles on National Forest. Approximately 11 miles of access roads would be improved or constructed.
Project Summary
Location Summary:
Whitley City substation on the east side of US 27, 0.4-mile south of KY 478 in McCreary County to the Wofford substation located on the north side of KY 779, 0.4 miles west of KY 26 in Whitley County.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/06/2019 |
Comment Period | 06/06/2019 |
Objection Period Start | 12/16/2020 |
Decision | 02/2021 (Estimated) |
Implementation | 02/2021 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Stearns Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
East Kentucky Power Cooperative Special Use Permit STE4062 Amendment
Decision Signed Date: 02/08/2021
Forests:
Daniel Boone National Forest
Districts:
Stearns Ranger District
States:
Kentucky
Counties:
McCreary
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Laurie Smith
3320 Highway 27 N
Whitley, KY 42653
606-376-5323
lauriesmith@fs.fed.us
Last Updated: 2/8/2021