Flat Rock Ridge and Gobblers Arch Trail Reroutes
The proposed project would reroute approximately 2,741 feet in two sections of trail #616 and approximately 2,049 feet in two sections of trail #636.
Project Summary
Location Summary:
Trail #616 is on the Wiborg quadrangle, less than a quarter mile North of Hwy 27 Sheltowee Trace trailhead. Trail #636 is on the Bell Farm quadrangle, less than a quarter mile South of Hemlock Grove.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/03/2020 |
Decision | 08/2020 (Estimated) |
Implementation | 09/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Stearns Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management; Scenery Management
Current Status:
Completed
Project Decision Information
Flat Rock Ridge and Gobblers Arch Trail Reroutes
Decision Signed Date: 08/17/2020
Forests:
Daniel Boone National Forest
Districts:
Stearns Ranger District
States:
Kentucky
Counties:
McCreary
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kathryn Fitzsimmons
3320 Highway 27 N
Whitley, KY 42653
606-376-5323 x125
kathryn.fitzsimmons@usda.gov