Aerial Retardant Delivery Systems
Appendix C—Final Setup Tasks
Meet with all personnel to give them an overview of operations, both
from an overall perspective and from a job-specific perspective.
- Check out the grid setup.
- Mark grid points.
- Transport supplies (cups, lids, bags, pickup boxes) to the
grid.
- Set up camera locations.
- Set up the weather station.
- Set up the weighing station.
- Establish an inside work area for data reduction and sample
analysis.
- Establish a washdown area, set up Fold-Da-Tanks, and plumb
the electric pump.
- Install instruments in the airtanker.
- Check out the mixing plant. This could possibly be done by
local personnel.
- Set up grid markers.
- Whitewash two 4 by 8 sheets of plywood.
- Secure panels in an
upright position at each end of the grid.
- Document panel locations.