Contract Clauses
The following is an excerpt from a Forest Service contract for construction:
I-## ACCIDENT PREVENTION (FAR 52.236-13) (NOV 1991)
- Whenever the Contracting Officer becomes aware of any noncompliance
with these requirements or any condition which poses a serious or
imminent danger to the health or safety of the public or Government
personnel, the Contracting Officer shall notify the Contractor orally,
with written confirmation, and request immediate initiation of corrective
action. This notice, when delivered to the Contractor or the Contractor's
representative at the work site, shall be deemed sufficient notice
of the noncompliance and that corrective action is required. After
receiving the notice, the (continued)
|