Contract Clauses

The following is an excerpt from a Forest Service contract for construction:

I-## ACCIDENT PREVENTION (FAR 52.236-13) (NOV 1991)

  1. (continued) Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.