Contract Clauses
The following is an excerpt from a Forest Service contract for construction:
I-## ACCIDENT PREVENTION (FAR 52.236-13) (NOV 1991)
- (continued) Contractor shall immediately
take corrective action. If the Contractor fails or refuses to promptly
take corrective action, the Contracting Officer may issue an order
stopping all or part of the work until satisfactory corrective action
has been taken. The Contractor shall not be entitled to any equitable
adjustment of the contract price or extension of the performance schedule
on any stop work order issued under this clause.
|