Aspen Skiing Company Communication Projects 2025
Installation of 11 Cellular Towers at 10 sites on National Forest lands at Aspen Skiing Company Resorts; Aspen Mountain, Aspen Highlands, Buttermilk, Snowmass. Including associated utilities (power, fiber optics) for each site.
Project Summary
Location Summary:
Various locations, all within the Special Use Permit Area for Aspen Skiing Company Resorts; Aspen Mountain, Aspen Highlands, Buttermilk and Snowmass.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/07/2024 |
Comment Period | 08/07/2024 |
Decision | 04/2025 (Estimated) |
Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
West Zone/Aspen Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Aspen Skiing Company Communication Projects 2025
Decision Signed Date: 04/15/2025
Forests:
White River National Forest
Districts:
West Zone/Aspen Ranger District
States:
Colorado
Counties:
Pitkin
Legal Land Description:
Range 85w, Township 10s Sections 9, 10,12,13, 15, 22, 23,27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Monte Lutterman
620 Main Street
Carbondale, CO 81623
970-404-3164
monte.lutterman@usda.gov
Last Updated: 4/16/2025