Great River Energy Transmission Line Amendment #14
Amendment to permit to construct electric transmission line along Itasca County Highway 7 corridor. This is outside the Leech Lake Band of Ojibwe reservation boundary
Project Summary
Location Summary:
Along Itasca County Hwy 7, SW of Scenic State Park
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/26/2019 |
Decision | 07/2019 (Estimated) |
Implementation | 11/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Deer River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Great River Energy Transmission Line Amendment #14
Decision Signed Date: 07/24/2019
Forests:
Chippewa National Forest
Districts:
Deer River Ranger District
States:
Minnesota
Counties:
Itasca
Legal Land Description:
T60N, R26W, SE1/4 SW1/4 Sec 4T60N, R26W SE1/4 SW1/4 Sec 3T60N, R26W, SE1/4 SE1/4 Sec 3T60N, R26W SW1/4 Sec 1
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Donna Schackman
1235 Division Street
Deer River, MN 56636
218-335-8615
djschackman@fs.fed.us
Last Updated: 7/25/2019