Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/05/2024 |
| Decision | 12/2024 (Estimated) |
| Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (20), 36 Cfr 220.6(E)(20); 32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cabinet Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Road Management
Project Activity:
Road Decommissioning; Road Maintenance; Road Improvements/Construction; Watershed Improvements
Project Decision Information
Rock Creek Road Realignment
Decision Signed Date: 12/30/2024
Forests:
Kootenai National Forest
Districts:
Cabinet Ranger District
States:
Montana
Counties:
Sanders
Legal Land Description:
Sections 10, 15, 22, and 27, T 26 N, R 32 W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Rossel
2693 MT Hwy 200
Trout Creek, MT 59874-9503
406-827-0726 (Cabinet RD)
Christopher.Rossel@usda.gov
Last Updated: 12/30/2024