The King Kong project area is located northeast of Troy, Montana. The project area is located east of O’Brien Creek and north of the Kootenai River.
Project Milestones:
| Milestone | Date |
|---|---|
| NEPA Start Date | 5/24/2024 |
| Finding/Decision Date | 9/15/2025 |
Expected Analysis Type:
Categorical Exclusion
Categorical Exclusion:
USDA-47d-USFS
Lead Management Unit:
Three Rivers Ranger District
Project Purpose:
Vegetation management (other than forest products); Wildlife, fish, rare plants
Project Decision Information
Decision Signed Date: 9/15/2025
States:
Montana
Counties:
Lincoln
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lisa Osborn
c/o Three Rivers Ranger District
12858 US Hwy 2
Troy, Montana 59935
406-293-4693
lisa.osborn@usda.gov
Last Updated: 6/17/2026