Rocky Pine Fuels Reduction
Hazardous fuels reduction on 1,530 acres utilizing harvest, excavator and hand piling, underburning and precommercial thinning.
Project Summary
Location Summary:
Pine Creek
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/15/2008 |
| Objection Period Start | 04/20/2008 |
| Decision | 07/2008 (Estimated) |
| Implementation | 10/2008 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Categorical Exclusion:
32.2 (10)
Special Authority:
Hfra Title I: Wildland-Urban Interface
Lead Management Unit:
Three Rivers Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Fuels Management; Forest Products
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Completed
Project Decision Information
Rocky Pine Hazardous Fuels Reduction
Decision Signed Date: 07/07/2008
Forests:
Kootenai National Forest
Districts:
Three Rivers Ranger District
States:
Montana
Counties:
Lincoln
Legal Land Description:
T33N & T34N, R34W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Eric Dickinson
12858 US Hwy 2
Troy, MT 59935-8750
(406)295-4693 x4126
edickinson@fs.fed.us
Last Updated: 8/8/2008