Troy Mine Revised Reclamation Plan
Troy Mine, Inc.of Troy, MT has proposed to revise the Reclamation Plan for its copper and silver mining and milling operation.
Project Summary
Location Summary:
Fifteen miles south of Troy, Montana in the Lake Creek drainage.
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 04/14/2011 |
| DEIS NOA in Federal Register | 05/20/2011 |
| FEIS NOA in Federal Register | 06/29/2012 |
| Decision | 09/2012 (Estimated) |
| Implementation | 05/2016 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kootenai National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Record of Decision for Troy Mine Revised Reclamation Plan
Decision Signed Date: 09/12/2012
Legal Notice Date: 10/14/2012
Forests:
Kootenai National Forest
Districts:
Three Rivers Ranger District
States:
Montana
Counties:
Lincoln
Legal Land Description:
T28N, R33W, Sections 5 & 6; T29N, R33W, Sections 5, 6, & 7; T29N, R34W, Sections 12, 13, 14, 23, 24, 25, 26, 35, & 36; and T30N, R33W, Sections 31 & 32, PMM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bobbie Lacklen
31374 US Highway 2
Libby, MT 59923-3022
406-283-7681
blacklen@fs.fed.us
Last Updated: 10/15/2012