Hellroaring Fat Tire Plan of Operations
Exploration drilling on MMG's claims in Hellroaring Creek, including one drill site with up to three drill holes. Drilling would be off the side of open National Forest System Road (NFSR) 745, Hellroaring Creek Road.
Project Summary
Location Summary:
Hellroaring drainage off of existing open NFSR 745
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/27/2013 |
| Comment Period | 02/27/2013 |
| Decision | 08/2013 (Estimated) |
| Implementation | 09/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Three Rivers Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Hellroaring Fat Tire Exploration Plan of Operations DM
Decision Signed Date: 08/08/2013
Forests:
Kootenai National Forest
Districts:
Three Rivers Ranger District
States:
Montana
Counties:
Lincoln
Legal Land Description:
Section 35, T36N, R34W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Lynn Hagarty
12858 US Hwy 2
Troy, MT 59935-8750
406-283-7502
lhagarty@fs.fed.us
Last Updated: 6/29/2015