Revision Process Timeline
For additional information and supporting documents related to the Revision Process Timeline, please visit our Document Library page.
Pre-Assessment (2021-2022)
Internal preparation to initiate forest plan revision
Assessment (winter 2021/22-summer 2023)
- Evaluate relevant data and information on existing conditions, roles and contributions, and trends
- Start natural range of variation modeling; wild and scenic river eligibility; species of conservation concern process; recreation opportunity spectrum and scenery management systems mapping; timber suitability and modeling; and wilderness inventory and evaluation
- Release Draft Assessment (summer 2023)
- Release Draft Preliminary Need to Change (summer 2023)
Plan Development and Scoping the Proposed Action (summer 2023-winter 2023/24)
- Timber suitability and monitoring
- Establish desired conditions and other plan components for all resources
- Map all proposed land allocations, such as geographic areas, management areas, designated areas, desired recreation opportunity spectrum settings and scenic integrity objectives
- Identify suitabilities across the landscape
- Develop a proposed plan monitoring program
- Release Preliminary Need to Change (winter 2024)
- Scope the Proposed Action (winter 2024)
Develop Draft Environmental Impact Statement and Draft Forest Plan (winter 2023/24-fall 2025)
- Review public comments from scoping
- Develop alternatives
- Develop the environmental impact statement and analyze the effects on resources of each of the alternatives.
- Release the Draft Environmental Impact Statement (fall 2025)
Develop Final Environmental Impact Statement and Draft Record of Decision (fall 2025-winter 2026/27)
- Analyze and respond to public comments from the Draft Environmental Impact Statement
- Select a preferred alternative
- Develop biological assessment on the selected alternative and consult with U.S. Fish and Wildlife Service
- Release Final Environmental Impact Statement and Draft Record of Decision (winter 2026)
Objection Process and Final Record of Decision (winter 2026/27-spring 2027)
- Objection period, review of objections, and resolution meeting
- Release final record of decision and revised plan (spring 2027)
- Begin plan implementation and monitoring!