T-150 Reconstruction
The T-150 administrative facility is used by the Lolo NF for a variety of purposes but has been condemned. The proposed reconstruction aims to provide a usable facility while maintaining the historic characteristics that define the current building.
Project Summary
Location Summary:
Southeast end of Fort Missoula
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/14/2025 |
Decision | 04/2025 (Estimated) |
Implementation | 05/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (21), 36 Cfr 220.6(E)(21)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Missoula Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
T-150 Reconstruction
Decision Signed Date: 04/30/2025
Forests:
Lolo National Forest
Districts:
Missoula Ranger District
States:
Montana
Counties:
Missoula
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ann Hadlow
24 Fort Missoula Road
Missoula, MT 59804
406-329-3809
ann.hadlow@usda.gov
Last Updated: 5/2/2025