Westside Roadside Timber Salvage
Commercial and Personal use treatment of approximately 95 acres of dead and dying timber within 150 feet of road shoulder along portions of Forest Service Roads 4349, 2190, and 2192
Project Summary
Location Summary:
Portions of Westside Bypass and Archibald Loop roads, Seeley Lake Ranger District, Lolo National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/24/2012 |
| Comment Period | 06/24/2012 |
| Decision | 12/2012 (Estimated) |
| Implementation | 06/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Seeley Lake Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Vegetation Management (Other Than Forest Products); Forest Products
Project Activity:
Forest Vegetation Improvements; Road Maintenance; Timber Sales (Salvage)
Current Status:
Completed
Project Decision Information
Westside Roadside Salvage Project
Decision Signed Date: 12/05/2012
Forests:
Lolo National Forest
Districts:
Seeley Lake Ranger District
States:
Montana
Counties:
Missoula
Legal Land Description:
T17N, R15W, Sections 7, 18, 29 and 30
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Joshua Angert
3583 Highway 83
Seeley Lake, MT 59868
406-329-3714
jangert@fs.fed.us