Clearwater Loop Rd 4370 Avalanche Culvert Replacement & Morrell Creek Bridge Replacement
Replace bridge on Morrell Creek, relocate 500 feet of roadway at the bridge approaches to place the bridge at a more stable location on the stream. Replace and relocate culvert on Clearwater Loop Road 4370, 75 feet upstream of existing structure.
Project Summary
Location Summary:
Clearwater Loop Road 4370 at mile mark 8.2. Morrell Bridge Road 4381 at mile mark 0.1.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/14/2014 |
| Decision | 05/2014 (Estimated) |
| Implementation | 06/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Seeley Lake Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Watershed Management
Project Activity:
Road Maintenance
Current Status:
Cancelled
Forests:
Lolo National Forest
Districts:
Seeley Lake Ranger District
States:
Montana
Counties:
Missoula; Powell
Legal Land Description:
Bridge: T17N, R15W, Section 1 Culvert: T19N, R15W, PB47
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nancy Taylor
3583 Highway 83
Seeley Lake, MT 59868
406-329-3772
ntaylor@fs.fed.us
Last Updated: 10/2/2014