Powderhorn West End Lift Replacement
Replace West End chairlift, conduct associated grading and tree clearing, relocate existing ski patrol yurt, construct new ski run with access road and utilities.
Project Summary
Location Summary:
Powderhorn Mountain Resort in Mesa, CO
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/2025 (Estimated) |
Decision | 11/2025 (Estimated) |
Implementation | 12/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Grand Valley Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Special Use Management
Project Activity:
Developed Site Management; Special Use Authorizations
Current Status:
Developing Proposal
Forests:
Grand Mesa, Uncompahgre and Gunnison National Forests
Districts:
Grand Valley Ranger District
States:
Colorado
Counties:
Mesa
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Timothy Wise
2777 Crossroads Blvd, Suite 1
Grand Junction, CO 81506
970-263-5802
timothy.wise@usda.gov
Last Updated: 7/7/2025