Teocalli Ridge Trail
Relocation of approximately8,431 linear feet to more sustainable location. Reconstruction / Restoration of existing portioins of trail if funding permits. Installation of drainage structures and erosion control measures
Project Summary
Location Summary:
Teocalli Ridge Trail above the Brush Creek drainage (NFST 557)
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/10/2012 |
Comment Period | 02/10/2012 |
Decision | 07/2012 (Estimated) |
Implementation | 09/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gunnison Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management; Watershed Management
Project Activity:
Trail Management; Travel Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Teocalli Ridge Trail
Decision Signed Date: 07/13/2012
Forests:
Grand Mesa, Uncompahgre and Gunnison National Forests
Districts:
Gunnison Ranger District
States:
Colorado
Counties:
Gunnison
Legal Land Description:
T 13 S, R 85W, Sec 14, 23
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Greg Austin
216 N. Colorado
Gunnison, CO 81230
970-642-4402
gpaustin@fs.fed.us