Iron Fen Ditch Restoration Project
Restore groundwater hydrologic regime of portion of the Iron Fen that is impaired by a ditch. Install flow control structure in current ditch and manage flow through wetland recapturing the flow once it reaches an old road alignment downslope.
Project Summary
Location Summary:
N.M.P.M T 14S R86W Section 6: NW¼SE¼
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/15/2012 |
| Comment Period | 04/15/2012 |
| Decision | 08/2013 (Estimated) |
| Implementation | 10/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (7), 36 Cfr 220.6(E)(7)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gunnison Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Current Status:
Completed
Project Decision Information
Mount Emmons Iron Fen Restoration Project
Decision Signed Date: 08/30/2013
Forests:
Grand Mesa, Uncompahgre and Gunnison National Forests
Districts:
Gunnison Ranger District
States:
Colorado
Counties:
Gunnison
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Murphy
216 N. Colorado
Gunnison, CO 81230
719-852-6221
jrmurphy@fs.fed.us
Last Updated: 9/9/2013