Imogene Pass Bridge Crossings #3, 4 and 5
Due to failed bridge inspections, install three new wooden bridges with slightly larger spans over the top of the existing wooden bridges on Imogene Pass Road (NFSR 869). The fourth bridge on NFSR 869 will be replaced with an armored rocky ford.
Project Summary
Location Summary:
Norwood Ranger District,Imogene Pass Road
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/22/2020 |
Decision | 01/2021 (Estimated) |
Implementation | 07/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Norwood Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Watershed Management
Project Activity:
Road Improvements/Construction; Watershed Improvements
Current Status:
Completed
Project Decision Information
Imogene Pass Bridge Crossings #3, 4 and 5
Decision Signed Date: 01/22/2021
Forests:
Grand Mesa, Uncompahgre and Gunnison National Forests
Districts:
Norwood Ranger District
States:
Colorado
Counties:
San Miguel
Legal Land Description:
T43N, R9W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Grant Clark
P.O. Box 388
Norwood, CO 81423
970-240-5438
grantclark@fs.fed.us
Last Updated: 2/3/2021