Navopache Linden Substation Permit
The purpose of this action is to issue a Communication Use Lease to Navopache Electric Co-op for 30 years for the installation and maintenance of radio monitoring equipment and antenna for monitoring electrical power use located at Linden.
Project Summary
Location Summary:
Linden Substation
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/19/2019 |
Decision | 09/2020 (Estimated) |
Implementation | 09/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lakeside Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Navopache Linden Substation Permit
Decision Signed Date: 09/23/2020
Forests:
Apache-Sitgreaves National Forests
Districts:
Lakeside Ranger District
States:
Arizona
Counties:
Navajo
Legal Land Description:
TOWNSHIP 10 NORTH, RANGE 21 EAST, SECTION 27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Tina Sorenson
2022 W White Mtn. Bl
Lakeside, AZ 85929
(928) 368-5111 ext 763
tsorenson@fs.fed.us
Last Updated: 9/23/2020