RB-38 Playa Restoration
Proposal to restore 1 playa basin by filling in pits which were dug in the 1970%u2019s. The spoil piles which remain from the original pitting will be placed back in the original borrow pits.
Project Summary
Location Summary:
The playa is located about 22 miles southeast of Texline, Tx.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/23/2016 |
Decision | 06/2016 (Estimated) |
Implementation | 10/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kiowa and Rita Blanca National Grasslands
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Species Habitat Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
RB-38 Playa Restoration Project
Decision Signed Date: 06/30/2016
Forests:
Cibola National Forest
Districts:
Kiowa and Rita Blanca National Grasslands
States:
Texas
Counties:
Dallam
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Benjamin Coble
714 Main St
Clayton, NM 88415
575-374-9652
blcoble@fs.fed.us
Last Updated: 6/30/2016