Central New Mexico Electric Coop - Sanchez
Extend existing aerial electric distribution line through NFS lands to a private residential inholding.
Project Summary
Location Summary:
From existing transmission pole located in Section 12 of T.4N., R.5E, going SW 432-feet and entering Section 13 of T.4N., R.5E., and continuing southwest 465-feet to the Forest boundary.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/06/2024 |
Decision | 06/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cibola National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
In Progress
Forests:
Cibola National Forest
Districts:
Mountainair Ranger District
States:
New Mexico
Counties:
Torrance
Legal Land Description:
T.4N., R.5E., Sections 12 & 13
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Richard Wilhelm
2113 Osuna Road, NE, Suite A
Albuquerque, NM 87113
505-346-3842
Richard.Wilhelm@usda.gov
Last Updated: 3/31/2025