2025 Forest Road 191I and 191F Realignment
Motor vehicle use on FS Road 191I and 191F is causing resource damage in the area. There is a need to realign portions of these segments to protect these resources and continue to provide safe roadways for public and administrative access.
Project Summary
Location Summary:
Mount Taylor Ranger District, McKinley County, South of I-40, Forest Service Road 191I and 191F
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/2025 (Estimated) |
Decision | 08/2025 (Estimated) |
Implementation | 08/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (20), 36 Cfr 220.6(E)(20); 32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mount Taylor Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Heritage Resource Management; Road Management
Project Activity:
Heritage Resource Management; Road Maintenance; Road Improvements/Construction
Current Status:
Developing Proposal
Forests:
Cibola National Forest
Districts:
Mount Taylor Ranger District
States:
New Mexico
Counties:
McKinley
Legal Land Description:
T13N, R16W - Sections 6, 7, 8 ; T13N R17W Sections 1, 12
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brittany Lewellen
1800 Lobo Canyon Rd
Grants, NM 87020
505-274-4519
Brittany.Lewellen@usda.gov
Last Updated: 6/20/2025