New Start - JaBob Mining Project Plan of Operations
The District Ranger signed the Decision for the New Start - JaBob Mining Project Plan of Operations. A copy of the Environmental Assessment, Finding of No Significant Impact, and Decision Notice can be found under the Analysis and Decision tabs.
Project Summary
Current Status:
Completed
Location Summary:
On National Forest System Lands, roughly one mile southwest of Pioneerville, Idaho, Boise County.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/01/2017 |
| Comment Period | 01/17/2020 |
| Objection Period Start | 11/02/2020 |
| Decision | 01/2021 (Estimated) |
| Implementation | 03/2021 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Boise National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Decision Notice, New Start - JaBob Mining Project Plan of Operations
Decision Signed Date: 01/04/2021
Forests:
Boise National Forest
Districts:
Idaho City Ranger District
States:
Idaho
Counties:
Boise
Legal Land Description:
T7N, R5E, sec 10
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Travis Whitman
1249 S. Vinnell Way, Suite 200
Boise, ID 83709
1-208-392-3719
travis.whitman@usda.gov