Bear Valley Borrow Source Development
There is a need to provide a cost-effective material source to facilitate road maintenance in the Bear Valley area. The proposal is to re-open and expand the existing borrow source located adjacent to Forest Road 579.
Project Summary
Current Status:
Completed
Location Summary:
The project is located 3/8 mile southwest of the intersection of Forest Road 582 and Forest Road 579.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/14/2021 |
| Comment Period | 04/14/2021 |
| Objection Period Start | 08/04/2021 |
| Decision | 12/2021 (Estimated) |
| Implementation | 05/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lowman Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Project Decision Information
Bear Valley Borrow Source Development
Decision Signed Date: 12/07/2021
Forests:
Boise National Forest
Districts:
Lowman Ranger District
States:
Idaho
Counties:
Boise
Legal Land Description:
Section 2 Township 12 North, Range 9 East.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeffrey Alexander
Highway 21
Lowman, ID 83637
208-373-4141
jalexander@fs.fed.us