Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/20/2023 |
| Decision | 07/2025 (Estimated) |
| Implementation | 05/2026 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cascade Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Horse Heaven Exploration Project
Decision Signed Date: 07/02/2025
Forests:
Boise National Forest
Districts:
Cascade Ranger District
States:
Idaho
Counties:
Valley
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ricky Wells
Highway 55
Cascade, ID 83611
208-373-4136
ricky.wells@usda.gov
Last Updated: 7/2/2025