Spout Spring Water Development
Restore an established water development to working conditions.
Project Summary
Current Status:
Completed
Location Summary:
Near NFSR 626 leading to Sagehen reservoir
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/01/2024 |
| Decision | 05/2024 (Estimated) |
| Implementation | 05/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (9), 36 Cfr 220.6(E)(9)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Emmett Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management
Project Activity:
Grazing Structural Improvements
Project Decision Information
Spout Spring Water Development
Decision Signed Date: 05/01/2024
Forests:
Boise National Forest
Districts:
Emmett Ranger District
States:
Idaho
Counties:
Gem
Legal Land Description:
R2E, T12N, Sec. 33 SE1/4 NW1/4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Daniel Nation
1805 Highway 16, #5
Emmett, ID 83617
208-365-7045
daniel.nation@usda.gov
Last Updated: 5/7/2024