Jackson Hole Mountain Resort Recreation Enhancements Project - 2023
Project proposal: replace Sublette lift; construct and modify ski runs, traverses, terrain parks, and visitor-service facilities; develop summer recreation opportunities; avalanche control infrastructure; fuels reduction.
Project Summary
Location Summary:
Adjacent to Teton Village, 8 mi northest of Jackson, WY.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/01/2023 |
Comment Period | 07/01/2023 |
Objection Period Start | 01/11/2024 |
Decision | 04/2024 (Estimated) |
Implementation | 04/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Jackson Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Recreation Management; Special Use Management; Climate Change Adaptation
Project Activity:
Fuel Treatments (Non-Activity Fuels); Special Use Authorizations
Current Status:
Completed
Project Decision Information
Jackson Hole Mountain Resort Recreation Enhancements Project - 2023
Decision Signed Date: 04/22/2024
Forests:
Bridger-Teton National Forest
Districts:
Jackson Ranger District
States:
Wyoming
Counties:
Teton
Legal Land Description:
Sixth principal meridian, T42N R117W Sections 13, 14, 15, 22, 23, 24
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mariah Radue
25 Rosencrans Lane
Jackson, WY 83001
307-739-5421