Lost River Electric Permit Amendment to bury powerline to Windy Devil Communication Site
Bury existing overhead powerline within the ROW for approximately 1/2 mile on NFS land.
Project Summary
Current Status:
Completed
Location Summary:
Windy Devil Communication Site, 3 miles west of Mackay, ID.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/05/2012 |
| Comment Period | 07/15/2012 |
| Decision | 10/2012 (Estimated) |
| Implementation | 10/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Challis National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Project Decision Information
Amendment to Permit LSR71 to Bury Powerline and Fiber Optic Cable
Decision Signed Date: 10/09/2012
Forests:
Salmon-Challis National Forest
Districts:
Lost River Ranger District
States:
Idaho
Counties:
Custer
Legal Land Description:
T. 7 N., R. 23 E., section 24
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gail Baer
1206 So. Challis Street
Salmon, ID 83467
208-756-5128
gbaer@fs.fed.us
Last Updated: 12/26/2012