New Tower at Jump off Peak Communication Site
Installation of a new 20 foot high metal tower and 4 foot diameter microwave dish and 9 foot square by 3.5 foot high concrete pad.
Project Summary
Location Summary:
Jump Off Peak Communcation Site, 5 miles southwest of Howe, ID.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/07/2012 |
Comment Period | 06/08/2012 |
Decision | 08/2012 (Estimated) |
Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Challis National Forest All Units
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
New Tower at Jump off Peak Communication Site
Decision Signed Date: 08/22/2012
Forests:
Salmon-Challis National Forest
Districts:
Lost River Ranger District
States:
Idaho
Counties:
Butte
Legal Land Description:
T5N, R28E, Section 15
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gail Baer
1206 So. Challis Street
Salmon, ID 83467
208-756-5128
gbaer@fs.fed.us