Mammoth Canyon Road Reclamation
The Lost River Ranger District (LRRD) is proposing to reclaim transportation routes by decommissioning twenty-one unauthorized routes and five closed system routes in the Alder Ck drainage, approximately 6 air miles south to southwest of Mackay, ID.
Project Summary
Location Summary:
Approximately 6 miles south to southwest of Mackay, ID.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/13/2015 |
Comment Period | 05/14/2015 |
Objection Period Start | 12/01/2016 |
Decision | 02/2017 (Estimated) |
Implementation | 08/2017 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lost River Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Road Management; Minerals And Geology
Project Activity:
Road Decommissioning
Current Status:
Completed
Project Decision Information
Mammoth Canyon Road Reclamation
Decision Signed Date: 02/16/2017
Forests:
Salmon-Challis National Forest
Districts:
Lost River Ranger District
States:
Idaho
Counties:
Custer
Legal Land Description:
T.6.N., R.23.E. Sections 10, 13, 14, 15, 22, 23, 24; T.6.N., R.24.E. Sections 25, 26, 27, 28, 30, 34, 35; and T.5.N., R.24.E. Section 3, Boise Meridian, Custer County, ID.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Glenwood Brittain
716 W Custer
Mackay, ID 83251
208-756-5169
gbrittain@fs.fed.us
Last Updated: 1/30/2020