Musgrove Exploration Drilling Project
Reopening of previously reclaimed exploration roads, construction of new temporary roads to facilitate development of 14 drill pads along the road prisms. Up to 42 core or reverse circulation holes would be drilled to assess mineral potential.
Project Summary
Location Summary:
Approximately 23 miles southwest of Salmon, ID. Musgrove Creek Drainage.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/02/2017 |
Comment Period | 03/02/2017 |
12/01/2017 | |
Objection Period Start | 07/13/2017 |
Decision | 12/2017 (Estimated) |
Implementation | 07/2018 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Cobalt Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Musgrove Exploration Drilling Project
Decision Signed Date: 12/01/2017
Forests:
Salmon-Challis National Forest
Districts:
Salmon-Cobalt Ranger District
States:
Idaho
Counties:
Lemhi
Legal Land Description:
Township 20 North, Range 18 East, Sections 22 and 27, Boise Prime Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Julie Hopkins
311 McPherson
Salmon, ID 83467
208-756-5279
juliehopkins@fs.fed.us
Last Updated: 12/14/2017