Bonneville Power Administration (BPA) Grouse Peak South Communication Facility Project
Issue a communications site lease to BPA at Grouse Peak South Communication Site to construct and operate a new self-supporting tower, equipment shelter, and propane tanks. Location is T14N, R20E, Sec22
Project Summary
Location Summary:
Grouse Peak South Communication Site located 7.5 miles east of Challis, Idaho.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/08/2017 |
Decision | 07/2018 (Estimated) |
Implementation | 07/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Challis-Yankee Fork Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Bonneville Power Administration Grouse Peak South Communication Facility
Decision Signed Date: 07/02/2018
Forests:
Salmon-Challis National Forest
Districts:
Challis-Yankee Fork Ranger District
States:
Idaho
Counties:
Custer
Legal Land Description:
T14N, R20E, Sec 20, Boise Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gail Baer
HC 63 Box 1669
Challis, ID 83226
208-756-5128
gbaer@fs.fed.us
Last Updated: 7/5/2018