Bear Creek Stream Restoration Project
Repairing the Bear Cr road by removing 1 mile of damaged road and constructing a new 1.1 mile section of road along the east side of Bear Creek
Project Summary
Location Summary:
The Bear Creek Stream Restoration Project is located in the Bear Creek drainage within the Big Lost River basin approximately 16 air miles southwest of Mackay, Idaho within Custer County.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/26/2019 |
Decision | 04/2020 (Estimated) |
Implementation | 07/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lost River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Road Management
Project Activity:
Road Decommissioning; Species Habitat Improvements; Species Population Enhancements; Road Maintenance; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Bear Creek Stream Restoration Project
Decision Signed Date: 04/09/2020
Forests:
Salmon-Challis National Forest
Districts:
Lost River Ranger District
States:
Idaho
Counties:
Custer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bart Gamett
716 W Custer
Mackay, ID 83251
208-588-2224
bgamett@fs.fed.us