Panther Creek Habitat Enhancement Phase 2
Phase II of a multi-phased project to address limiting factors for fish habitat in a low-gradient meandering stretch of Panther Creek. Installation of in-stream structures to improve habitat and hydraulics and collection of trees for restoration work
Project Summary
Location Summary:
Panther Creek below Musgrove and Moyer Creeks
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/22/2019 |
Decision | 08/2021 (Estimated) |
Implementation | 08/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Cobalt Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Panther Creek Habitat Enhancement Phase 2
Decision Signed Date: 08/09/2021
Forests:
Salmon-Challis National Forest
Districts:
Salmon-Cobalt Ranger District
States:
Idaho
Counties:
Lemhi
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kelly Schade
311 McPherson
Salmon, ID 83467
208-756-5229
kellyschade@fs.fed.us
Last Updated: 8/10/2021