Idaho Public Television and Teton Communications Site at Grouse Peak
Installation of a backup generator and propane tank at an existing communications site located Grouse Peak.
Project Summary
Location Summary:
Located on Grouse Peak North. Township 14North, Range 20East,section 10
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/18/2020 |
Decision | 12/2021 (Estimated) |
Implementation | 01/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Challis National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Idaho Public Television and Teton Communications Site at Grouse Peak
Decision Signed Date: 12/14/2021
Forests:
Salmon-Challis National Forest
Districts:
Challis-Yankee Fork Ranger District
States:
Idaho
Counties:
Custer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cassandra Kollenberg
1206 So. Challis Street
Salmon, ID 83467
208-756-5166
ckollenberg@fs.fed.us