Salmon-Challis Rock Source Project
Expansion of four existing rock source pits and development of five new rock sources (approximately 90 acres) across the forest to facilitate road maintenance needs.
Project Summary
Location Summary:
Located across the forest
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/18/2020 |
Decision | 08/2022 (Estimated) |
Implementation | 10/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Challis National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Salmon-Challis Rock Source Project
Decision Signed Date: 08/02/2022
Forests:
Salmon-Challis National Forest
Districts:
Salmon-Challis National Forest All Units
States:
Idaho
Counties:
Butte; Custer; Lemhi
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeffrey Hunteman
1206 So. Challis Street
Salmon, ID 83467
208-382-7400
jhunteman@fs.fed.us