BTAC Drilling Project
The Operator proposes to disturb up to a total of 230 acres by constructing 24 miles of temporary roads, 300-400 drill sites, up to 4 drill holes per site and staging in phases spread across ten years.
Project Summary
Location Summary:
Sections 5, 8, 9, 10, 16, 20, 21, 28, 29, and 32 of Township 22 North, Range 20 East (T22N, R20E), Sections 13, 14, 15, 16, 21, 22, 23 and 24, of T22N, R19E, Section 5 and 6 of T21N, R20E, Boise Prime
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/08/2021 |
Comment Period | 04/08/2021 |
Objection Period Start | 03/17/2022 |
Decision | 08/2022 (Estimated) |
Implementation | 08/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salmon-Cobalt Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
BTAC Exploration Drilling Project
Decision Signed Date: 08/01/2022
Forests:
Salmon-Challis National Forest
Districts:
Salmon-Cobalt Ranger District
States:
Idaho
Counties:
Lemhi
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Deanna Stever
311 McPherson
Salmon, ID 83467
208-768-7619
deanna.stever@usda.gov