Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/09/2021 |
Decision | 09/2022 (Estimated) |
Implementation | 09/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
North Fork Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
North Fork Sheep Creek Placer
Decision Signed Date: 09/01/2022
Forests:
Salmon-Challis National Forest
Districts:
North Fork Ranger District
States:
Idaho
Counties:
Lemhi
Legal Land Description:
: T.25N., R.22E., Sections 11 and 14, Boise Meridian, Lemhi County, Idaho.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Glenwood Brittain
11 Casey Rd.
North Fork, ID 83466
208-756-5169
glenwood.brittain@usda.gov
Last Updated: 9/7/2022