Muldoon Canyon Wetland Restoration
Relocate a section of the Muldoon Canyon Road (FS Road # 40510) that is negatively impacting streams, floodplains, wetlands, and riparian areas
Project Summary
Location Summary:
Muldoon Canyon watershed on the Lost River Ranger District approximately 19 air miles southwest of Mackay, Idaho
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/09/2021 |
Decision | 01/2023 (Estimated) |
Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lost River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Species Population Enhancements; Road Maintenance
Current Status:
Completed
Project Decision Information
Muldoon Canyon Wetland Restoration
Decision Signed Date: 01/05/2023
Forests:
Salmon-Challis National Forest
Districts:
Lost River Ranger District
States:
Idaho
Counties:
Custer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bart Gamett
716 W Custer
Mackay, ID 83251
208-588-2224