North Fork Burnt River Mining Supplemental EIS
Prepare a supplement to the April 2004 North Fork Burnt River Final Environmental Impact Statement to address the inadequacies identified by the United States District Court of Oregon, August 4, 2006.
Project Summary
Current Status:
Completed
Location Summary:
The North Fork Burnt River Watershed, Unity Ranger District, Wallowa-Whitman National Forest
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 02/21/2007 |
| DEIS NOA in Federal Register | 09/24/2010 |
| FEIS NOA in Federal Register | 09/07/2012 |
| Decision | 08/2012 (Estimated) |
| Implementation | 01/2013 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Whitman Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
North Fork Burnt River Mining
Decision Signed Date: 08/14/2012
Legal Notice Date: 09/07/2012
Forests:
Wallowa-Whitman National Forest
Districts:
Whitman Ranger District
States:
Oregon
Counties:
Baker
Legal Land Description:
T9S, 10S, 11S and 12S; R35E, 351/2E, 36E, and 37E; Willamette Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sophia Millar
1550 Dewey Avenue
Baker City, OR 97814
541-426-5540