Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 03/18/2008 |
| Comment Period | 02/05/2010 |
| Decision | 03/2011 (Estimated) |
| Implementation | 07/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Eagle Cap Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management; Wilderness Management
Project Decision Information
Rock Creek Bridge Replacement
Decision Signed Date: 03/15/2011
Legal Notice Date: 04/06/2011
Forests:
Wallowa-Whitman National Forest
Districts:
Eagle Cap Ranger District
States:
Oregon
Counties:
Union
Legal Land Description:
T 4S, R42E, Section 14, and T 3S, R45E, Section 29, WM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mary Emerick
201 East Second Street
Joseph, OR 97846
541-426-5536
memerick@fs.fed.us
Last Updated: 4/7/2011