Bruce Young Road Relocation
This project would allow a landowner to reroute an existing road outside of the riparian area which will cross the corner of Forest Service property for approximately 60 feet.
Project Summary
Current Status:
Completed
Location Summary:
Located near Forest Service Road 3106 and Pelican Creek
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/22/2012 |
| Comment Period | 05/22/2012 |
| Decision | 01/2013 (Estimated) |
| Implementation | 02/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
La Grande Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Land Ownership Management
Project Activity:
Watershed Improvements
Project Decision Information
Bruce Young Road Relocation
Decision Signed Date: 01/17/2013
Forests:
Wallowa-Whitman National Forest
Districts:
La Grande Ranger District
States:
Oregon
Counties:
Union
Legal Land Description:
T 2S, R 36E, Section 23 SE/NW
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Cindy Christensen
3502 Hwy. 30
La Grande, OR 97850
541-962-8501
cjchristensen@fs.fed.us
Last Updated: 1/31/2013