Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/14/2015 |
Decision | 08/2018 (Estimated) |
Implementation | 09/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (8), 36 Cfr 220.6(D)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pisgah Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Cancelled
Forests:
National Forests In North Carolina
Districts:
Pisgah Ranger District
States:
North Carolina
Counties:
Transylvania
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Linda Randolph
1001 Pisgah Hwy.
Pisgah Forest, NC 28768
828-622-3202
lrandolph@fs.fed.us
Last Updated: 9/30/2020