Pisgah-Canton Duke Transmission Line ROW Widening
Expansion of existing transmission line ROW and Hazard Tree Zones to 75 feet on both sides of the line for a total of up to 150 feet of combined ROW and Hazard Tree Zones (varies by Management Area).
Project Summary
Location Summary:
The project area is the existing approximately 8-mile powerline corridor from the southeast entrance to the Pisgah National Forest near the Sycamore Flats Recreation Area extending northwest to the Blue Ridge Parkway.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/19/2023 |
Comment Period | 05/30/2024 |
Objection Period Start | 01/2025 (Estimated) |
Decision | 02/2025 (Estimated) |
Implementation | 02/2025 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
National Forests In North Carolina All Units
Notice and Comment Regulation:
219 (2012)
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
In Progress
Forests:
National Forests In North Carolina
Districts:
Pisgah Ranger District
States:
North Carolina
Counties:
Haywood; Transylvania
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
James Owen
160 Zillicoa St.
Asheville, NC 28801
8288773265 ext. 233
james.owen@usda.gov
Last Updated: 1/22/2025