Jackrabbit Mountain Bike Trailhead Bridge Installation and Culvert Removal Project
Project will construct a new bridge from Jackrabbit Mountain Bike Trailhead to existing trail network over a causeway with an existing, failing culvert. Project also proposes to remove failing culvert and existing causeway while recontouring slopes.
Project Summary
Current Status:
Completed
Location Summary:
Adjacent to Jackrabbit Mountain Bike Trailhead at the causeway connecting the trailhead to primary trail network.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/30/2025 |
| Decision | 10/2025 (Estimated) |
| Implementation | 10/2026 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tusquittee Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Project Decision Information
Jackrabbit Mountain Bike Trailhead Bridge Installation and Culvert Removal Project
Decision Signed Date: 10/21/2025
Forests:
National Forests In North Carolina
Districts:
Tusquittee Ranger District
States:
North Carolina
Counties:
Clay
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Taylor Britt
123 Woodland Drive
Murphy, NC 28906
435-231-3462
Taylor.Britt@usda.gov
Last Updated: 10/21/2025