Choctaw Electric Cooperative 3 Phase Underground Line Installation FS Road 52680
Installation of approx. 1,500 feet of underground 3 phase distribution line along NFS Road 52680.
Project Summary
Location Summary:
North of Hochatown, OK near Lukfata Trail.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/04/2025 |
| Decision | 09/2025 (Estimated) |
| Implementation | 09/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kiamichi Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
In Progress
Forests:
Ouachita National Forest
Districts:
Kiamichi Ranger District
States:
Oklahoma
Counties:
McCurtain
Legal Land Description:
In Section 27, Township 4 South, Range 24 East, McCurtain County, Oklahoma.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jona Tucker
111 South State Highway 259-A
Broken Bow, OK 74728
580-494-6404
Jona.Tucker@usda.gov
Last Updated: 6/4/2025