AVECC Powerline ROW
Installation and maintenance of overhead powerlines, clearing and maintenance of associated Right-of-Way corridor (approximately 204 feet long and 40 feet wide.
Project Summary
Location Summary:
Township 2 North, Range 27 West, Section 24, Scott County, Arkansas
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/02/2025 |
Decision | 06/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Oden Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
In Progress
Forests:
Ouachita National Forest
Districts:
Oden Ranger District
States:
Arkansas
Counties:
Scott
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christopher Bay
1603 Hwy 71N
Mena, AR 71953
479-394-2382
Christopher.Bay@usda.gov
Last Updated: 4/23/2025